dougd wrote:So this is what I should have boughtInstead of these?
Unfortunately yes. ;( You must specify epoxy potting. You cannot trust the IP ratings in those descriptions as the descriptions are often copy-pasted from an older product to a new one.
Gary Martin wrote:To use this stuff you need to be ordering between January and March of the year you want to use it. That leaves plenty of time to get it, test it, return it if needed and get replacements.
I think you can safely go to June or maybe even July and still have time to test and get replacements. From that point on your going to have to realize that the rush is on and you may run into problems.
boarder3 wrote:I never left feedback for him. A lot of times he goes around website and sends you personal paaypal so you can't leave feedback or don't get return pokicy site gives you. That's what he did with me twice. Only time I paid through web site pixels were good 3 years ago and those are still good minimum failures. Last 2 shipments were same 3001 pixels which are injected were junk.
Ali Express is not allowed to do business in the state of Washington for some reason, so I'm not able to use it. I'm happy that he's willing to use Paypal as it's the only way I could use him.
Everyone gets to pick who they do business with. If a bunch of my pixels die this year I'll switch to another vendor, but so far I'm happy with Ray. Has anyone even found another vendor with better quality?
-=Steve
I agree ordering early is good, but sometimes money or time or even life in general does not allow for this comfortable margin. I think the bigger issue is that strings are showing up without seemingly any level of QA or testing. Buyer should have to send 1 string in 100 back for failure max-even that is poor quality. It would be in Ray's best interest to have as few come back as possible.
Has anyone done any failure analysis on the failed strings? Is there any common theme with respect to these failures? These strings aren't exactly complicated, it should be pretty easy to deturmine failures once open. Then feed this info back to Ray.
Just my 2 cents....
I agree and I'll be talking to Ray more about Quality Control among other things after the season is over. He has a large market in the US and if he wants to keep it he needs to put more into QA. However we need to understand that adding things like 24 to 72 hour burn-ins will add cost. So one question would be how much more per pixel are we willing to pay for additional testing and burn-in.
timon wrote:I agree and I'll be talking to Ray more about Quality Control among other things after the season is over. He has a large market in the US and if he wants to keep it he needs to put more into QA. However we need to understand that adding things like 24 to 72 hour burn-ins will add cost. So one question would be how much more per pixel are we willing to pay for additional testing and burn-in.
I don't think I would want to pay anymore than I am now, however that being said there are probably a lot of people with no time on their hands that would pay more, Ordering early gives me all kinds of time to play them bit I feel for the people that are having troubles especially at this time of the year.
I have seen a few posts that indicate you can pay for stuff from Ray with Paypal. When I checked out on Aliexpress, I did not see a Paypal option, I had to use a credit card. What am I missing?
msiebri wrote:I have seen a few posts that indicate you can pay for stuff from Ray with Paypal. When I checked out on Aliexpress, I did not see a Paypal option, I had to use a credit card. What am I missing?
His quotes give you the paypal option.
Tory
timon wrote:I agree and I'll be talking to Ray more about Quality Control among other things after the season is over. He has a large market in the US and if he wants to keep it he needs to put more into QA. However we need to understand that adding things like 24 to 72 hour burn-ins will add cost. So one question would be how much more per pixel are we willing to pay for additional testing and burn-in.
I guess that is what is confusing me....what can you imagine is failing after 24 hours with these? I have only has something similar, in my case I had used a solder flux that was susceptable to heat and himitdity combo and would become low impedance over time.
I cannot imagine why Ray would need to do a 24 hour burn in. Even more reason to perform FA on these, ASAP.
When i was working as a design engineer we preferred to do 48 to 72 hour burn-in at room temperature but that tied up too many resources. We solved that by setting up a burn-in room that cycled. We could do the equivalent burn-in in 8 hours so we got two batches of computer out each day per burn-in room.
The same could be done with pixels and controllers.