Help!!
I'm running vix 2.1.1.0.
I thought I had vixen all figured out and it has been running seq. fine, but now that I'm confguring seqs. into multiple programs, I'm getting the dreaded com port router error. Wierd thing is that I can switch between multiple programs using the play/stop button in the middle program manager window and it switches between and plays each prgram flawlessly. But when I set pc clock to force an auto program execution such as (9:30, 10:00, etc.), since I have them set to 30 minute intervals just as a test, it throws the com/router error everytime. I've setup each program to use the 'program profile', set the crossfade time to zero, removed all plug-ins from each of the seqs. and unchecked 'reset controllers' in preferences.
I downloaded and tried 2.5.0.8 and got the same result when executing program timers. Now I can't even get 2.5 to startup without an unhandled exception error, so I'm back to 2.1.
I'm pulling my hair out and we're getting ready to leave on a trip, so hoping I can get this resolved befroe I leave.
Thanks so much!
So i have recently confronted this, i think?
If you are trying have more than 1 schedule, each schedule playing a different program. Then you must be sure the first program finishes completely before the second one starts.
(Also i think you want to check rese controllers, but i might be wrong.)
I have this exact same problem. Does Vixen overlap sequences that start/end at the same time? For example, I have one that ends at 5:30pm and another that starts at 5:30pm. I am getting the same router startup/com port error that theavguy99 mentions. Since I can't schedule by the second (end at 5:29:59 and start next at 5:30:00), and I don't want a whole minute without anything running, what is the workaround?
jphaus wrote:I have this exact same problem. Does Vixen overlap sequences that start/end at the same time? For example, I have one that ends at 5:30pm and another that starts at 5:30pm. I am getting the same router startup/com port error that theavguy99 mentions. Since I can't schedule by the second (end at 5:29:59 and start next at 5:30:00), and I don't want a whole minute without anything running, what is the workaround?
I'm pretty sure you need some sort of minimum buffer time between programs so that Vixen can let go of them. My program runs 59:40 and is set to start every 60 minutes beginning at 5:30pm. until 10:00 p.m. (not 10:30). Then at 10:30, since the last hour long program started at 9:30 and went to 10:29:40, the sign-off sequence runs after which everything shuts down automatically.
Also, be sure you don't have the "fade between sequences" setting set to zero.
dirknerkle wrote:
Also, be sure you don't have the "fade between sequences" setting set to zero.
I changed to a 1-second cross-fade between sequences to see if that helps tonight. That seems like it might work to me because Vixen would open the next sequence while the previous one is still open (as long as that doesn't cause the same router/com error). My main program is only 12 minutes long, and loops over and over for 4 hours. It consists of 8 sequences within it and each one of those transitions fine. It's after that program ends and the next "shut down" sequence starts up that I get the problems.
I like your method of manually scheduling it over and over, but that would be time consuming for my short program, therefore I prefer the looping.
Will post my results with the cross-fade after tonight.
jphaus wrote:I changed to a 1-second cross-fade between sequences to see if that helps tonight. That seems like it might work to me because Vixen would open the next sequence while the previous one is still open (as long as that doesn't cause the same router/com error). My main program is only 12 minutes long, and loops over and over for 4 hours. It consists of 8 sequences within it and each one of those transitions fine. It's after that program ends and the next "shut down" sequence starts up that I get the problems.I like your method of manually scheduling it over and over, but that would be time consuming for my short program, therefore I prefer the looping.
Will post my results with the cross-fade after tonight.
The crossfade has been known to cause that problem, so I hope it works for you. Doesn't for me -- I've tried 3 different PCs. Setting it to zero eliminates the problem.
If you want a little more space in your show between starts of programs, just add another sequence to the program, but leave it blank. You don't even need music. If you needed a minute, just create a 60-second sequence using your normal plug-in, and leave all the cells blank. Insert it as the last part of your program and save it. All it will do is create an extra minute delay. Or make it 5 minutes, and put it in twice if you want 10 minutes, etc.
There are other workarounds to solve this kind of problem... and you can still leave the cross fade set to zero.
-dave
Setting cross-fade to 1 second didn't help -- same problem for me. :confused: