I purchased some GECE's for my roof line which consists of 5 strands. I positioned the controller in the attic central to the roofline but my outer strands still have a lead length of about 30 feet. The pixels are doing all kinds of weird flickering and not responding to commands correctly. I know it is a voltage drop issue. My question is what are my options in this scenario? I cannot reach all strands without having some lead lengths 20 to 30 feet.
- Matt
Are you doing any power injection? You can splice in the power block you cut from the ends of the gece strands to supply power. Don't run V+ from the controller. Simply splice in V+ from the wall wart. However, you MUST connect V- from the wall wart back to the controller. Of course, run data from the controller as well.
Also, are you running your outer strands where plugs meet in the middle? If using e681, you can change settings so that even if your pixels are wired backwards, you can still address them the same.
If none of that works, you may have to cut off a couple of pixels and install them along the way, setting null pixels in the e681 config.
Depending on the cable you use, you can accomplish pretty long cable runs. My longest run (cat 6 - 1 pair each for +/-/data) was about 50ft without any problems.
Very important to power up the E68x AFTER you connect the GECE - They can act very strange if done the other way around.